Nov 2019 - Jan 2020
Civil work
Heavy equipment installing water, sanitary and sewer mains.
-
Nov 2019 - Jan 2020
Concrete Foundations
Concrete truck traffic during concrete pours.
-
Dec 2019 – Apr 2020
Steel erection
Truck traffic due to ongoing steel deliveries.
-
Jan - May 2020
Concrete slab pours
Heavy truck traffic on concrete pour days.
(1 pour per month) -
Jan - June 2020
Roofing
Truck traffic due to ongoing deliveries.
-
July - Nov 2020
Envelope
Truck traffic due to ongoing deliveries.
-
July 2020 - May 2021
Interior Fit-up
Truck traffic due to ongoing deliveries.
-
July - Nov 2020
Parking Lot
Heavy equipment preparing/compacting roadways & parking lot.
-
Aug - Oct 2020
Landscaping
Truck traffic due to ongoing deliveries.
Construction equipment on site completing final grade. -
May 2021
Completion
Estimated completion.