• Nov 2019 - Jan 2020

    Civil work

    Heavy equipment installing water, sanitary and sewer mains.

  • Nov 2019 - Jan 2020

    Concrete Foundations

    Concrete truck traffic during concrete pours.

  • Dec 2019 – Apr 2020

    Steel erection

    Truck traffic due to ongoing steel deliveries.

  • Jan - May 2020

    Concrete slab pours

    Heavy truck traffic on concrete pour days.
    (1 pour per month)

  • Jan - June 2020

    Roofing

    Truck traffic due to ongoing deliveries.

  • Feb - Sep 2020

    Envelope

    Truck traffic due to ongoing deliveries.

  • Feb - Apr 2020

    Interior Fit-up

    Truck traffic due to ongoing deliveries.

  • June - Sept 2020

    Parking Lot

    Heavy equipment preparing/compacting roadways & parking lot.

  • Aug - Oct 2020

    Landscaping

    Truck traffic due to ongoing deliveries.
    Construction equipment on site completing final grade.

  • May 2021

    Completion

    Estimated completion.